Project Description Estimated Cost
PROGRAM MANAGEMENT @ WATERWORKS PLANTS
Facility Plan Update 1,000
PEP Program Management - Phase III 3,000
Subtotal 4,000
BALDWIN PLANT IMPROVEMENTS
Residuals/Reservoir 6,300
12,000
Sludge Drying Beds  
Subtotal 18,300
CROWN PLANT IMPROVEMENTS
Crown Intake Rehabilitation 5,000
Subtotal 5,000
MORGAN PLANT IMPROVEMENTS
Demolition of Existing West Reservoir 2,000
West Reservoir (PDR 7) 3,500
29,000
Chemical Facility (PDR 14) 5,000
(includes Hypogeneration & Machine Shop/Storeroom Bldg.) 6,300
10,000
Raw Water Pumps 2,000
8,000
Intake Crib and Flushing Improvements 870
5,800
New Entrance Roadway 1,500
Subtotal 73,970
NOTTINGHAM PLANT IMPROVEMENTS
Raw Pumping & Intake/Crib Rehabilitation 2,580
17,180
Rehabilitation & Expansion Finished Water Reservoir  3,120
20,800
Miscellaneous Upgrades @ Nottingham 1,500
Subtotal 45,180
MISCELLANEOUS PLANT IMPROVEMENTS
SCADA System Replacement 8,000
Control Sytem Upgrades for PCCS 2,500
Knowldege Capture for PCCS 1,000
Future Plant Projects (Post PEP) 1,000
8,000
Roof Rehab - General 1,000
4,500
Electrical/Switchgear Improvements 1,000
Sustainability Program 2,000
Energy Management 500
4,000
Subtotal 33,500
SUPPLY MAINS
Aurora Road Water Supply Main - Phase I (Broadway 2nd Feed) 7,900
Cook Road Water Main (Olmsted Twp.) 2,500
Streetsboro Road Water Main (4th High Phase I) 300
1,400
Broadview Road Water Main (4th High Phase II) 1,000
5,500
Transmission Valve Renewal Program 1,000
5,000
Trunk Main Renewal Program - Phase I (Concrete Mains) 1,000
3,000
6,000
Trunk Main Renewal Program - Future 3,000
21,000
Brecksville Distribution Water Quality Improvements 500
Bagley Road Restricted Water Mains 250
South Woodland Express Main 1,825
Subtotal 61,175
DISTRIBUTION MAINS
Distribution Main Replacement - Future Years (Cleveland) 9,000
Suburban Water Main Renewal Program 10,000
Distribution System Enhancement Program (DEP) - Systemwide 120,000
Subtotal 139,000
CLEANING AND LINING WATER MAINS
Cleaning & Lining - Distribution Main Program - 2009 6,105
Cleaning & Lining - Distribution Main Program - 2010 6,300
Cleaning & Lining - Distribution Main Program - Future Years 54,000
Subtotal 66,405
SECONDARY STATION IMPROVEMENTS
Water Tank Rehabilitation - Cycle E 7,300
Secondary Site Improvements - Cycle F 6,000
Future Secondary Site Improvements 12,000
Secondary Station (Distribution) Rehabilitation 1,500
12,000
Aurora Road Pump Station (Broadway 2nd Feed) 1,500
7,000
Cook Road Tower(Olmsted Twp.) (GES Design) 7,100
Distribution System Water Quality Monitoring & Secondary Station  3,700
Rechlorination Facilities
Broadview Road Tower (4th High Phase I) 3,000
Streetsboro Road Pump Station  (4th High Phase I) 2,000
Broadview Road Pump Station (4th High Phase II) 3,000
Subtotal 66,100
BUILDING AND TECHNOLOGY IMPROVEMENTS
General Engineering Services - Phases VI- VIII 15,000
Additional Security Items 500
Meter Project (AMR + Meter Rightsizing) 5,000
75,000
Renovations @ 1201 Lakeside Ave. - Ph. I 1,000
Renovations @ 1201 Lakeside Ave. - Ph. II 700
Facilities Improvements 250
5,000
Wind Farm 2,000
8,000
800 Megahertz 445
Technology Projects 10,000
Data Warehouse & Integration 1,000
Automated Vehicle Locator (AVL) 450
E.A.M. Replacement (Ellipse/work mgmt.) 1,000
7,000
Subtotal 132,345
  
CLEVELAND ROADWAY PROJECTS
East 176th Street 162
Tower City Center Water Infrastructure 400
Flats East Bank 740
West 150th Street Reconstruction 250
Rehab of E. 30 th Street 888
Bellare Road Rehab - Ph. II 142
Broadway Ave. Rehab 565
West 77th Street Bridge 108
Detroit Ave. Streetscape 96
Rehabilitation of Superior Ave. 702
Rehabilitation of Central Ave. 242
Various City of Cleveland Roadway Projects 18,500
Subtotal 22,795
NON-PROGRAMMED CAPITAL PROJECTS
Non-programmed capital projects allocation (2013 - 2018) 55,000
Subtotal 55,000
TOTALS 722,770

Questions? Call customer service at 1.216.664.3130 |
Privacy & Security
Copyright City of Cleveland, Division of Water. All rights reserved.
Proud Member of the City of Cleveland-Department of Public Utilities